Major trenching works are underway on site to provide underground ducting for the air conditioning, electrical connections and plumbing.
Preparations are well advanced to may the slab in the School of Arts now that underpinning has been completed
The formwork for the mezzanine level is now completed and the support columns will be poured in the next few days. The columns are clearly visible as the yellow poles in this photograph.
Trench for the airconditioning ducting
This will be the Youth area when the building is completed. In the middle of the photo you can make out the reinforced support structures for the main support columns.