Official Opening

The Ingleburn Centre will be officially opened during a family gala day on 7 March 2009 at about 2pm.

The new library will go "live" on the 9 March 2009, opening at 9.30am.

To enable the relocation of book stock and IT resources we will be closing the temporary branch in Carlisle St from 2 March 2009.

We're all very excited!

Monday, January 19, 2009

Finishing Off

The construction phase is now into the final stretch with final exterior groundwork and internal finishes, joinery and flooring now well advanced.








The trees have been planted


Circular stairway balustrade is being installed



Quiet study rooms on the mezzanine





Handrail detail








Friday, December 19, 2008

Building the Collection

While the building works are forging ahead, the Library team have been busy building the collection for the new branch.

Items are now being boxed up, labled and arranged for the removalists. Countless boxes of new books, DVD's and CD's have been purchased and processed over the last 12 months. The following photos will give you an idea of just how much space 10,000 items takes up.










Thursday, December 18, 2008

December 17

There has been a great deal of activity taking place on site over the last few weeks and keen construction watchers may have noticed the installation of some of the exterior graphics this week. Interior details are also progressing rapidly.




The concrete flow coat has been poured in the library entrance ready for polishing








Light fittings have been installed








Thursday, December 4, 2008

December

Lots of detailed work taking place on site as we move ever closer to completion.






Decking off Meeing rooms 1 & 2

















Staff work room and offices
















The manjor joinery components for the serivce desks are on site awaiting installation






Glass balustrade has been installed on the mezzanine








Friday, November 14, 2008

November